INVENTORY, MRP AND PURCHASING GUIDE

Inventory, MRP and
purchasing for job shops

MRP takes what you have promised to ship, subtracts what is on the shelf and already on order, and tells purchasing what to buy and when, using each part’s bill of materials and lead times. In a job shop, much material is bought for a specific job rather than stocked. The key decision is which items to plan from stock and which to buy per job, and that is mostly configuration.

MRP IN ONE WORKED EXAMPLE

From an order to a purchase order.

The arithmetic is simple. The value is doing it for every open job, every day, without anyone retyping the bill of materials.

  1. Demand

    A customer orders 50 brackets. Each needs a 4-inch piece of 6061 aluminum bar and two threaded inserts.

  2. Gross need

    50 pieces at 4 inches is 200 inches of bar, about 17 feet before saw kerf and cut allowance, plus 100 inserts.

  3. Net need

    The rack holds 3 feet of the right bar and the bin holds 40 inserts. Nothing is on order. Net need is roughly 14 feet of bar plus allowance, and 60 inserts.

  4. Planned order

    The supplier’s lead time and the job’s saw date decide when the PO must go out. The system suggests it; purchasing confirms supplier, price and minimum buy.

WHY JOB SHOPS BUY DIFFERENTLY

Not everything belongs in inventory.

BUY TO THE JOB

Material that belongs to one order

  • Uncommon grades, sizes or customer-specified material.
  • Outside processing such as plating or heat treat, bought as a service on a PO tied to the job’s operation.
  • Customer-supplied material, received against the job at no cost but still tracked.

PLAN FROM STOCK

Material you use every week

  • Common bar, sheet and hardware, with a reorder point.
  • Remnants and drops worth reusing, recorded by length so the saw can find them.
  • Consumables, kept simple and out of job costing.

Most ERPs can do both. The configuration choice per item, stocked or bought to the job, matters more than which product you choose.

AT THE RECEIVING DOCK

Record it once, when it arrives.

Receiving is the cheapest moment to capture what quality, costing and traceability will need later. After the material is cut, it is too late.

What to record when material is received
RecordWhy it matters later
PO line and jobShows short or late receipts on the jobs waiting for them
Heat or lot numberLinks every part made from this material to its source
Material certificationThe mill test report a customer or auditor may ask for, attached rather than filed separately
Quantity and lengthBar and sheet are consumed by length or area, not by count
Supplier and dateSupplier delivery and quality history, for the next buying decision

The heat number is the start of the traceability chain. See quality and traceability

ILLUSTRATIVE SCENARIO · A COMPOSITE, NOT A CLIENT

A short shipment of bar stock

A shop receives 12 of the 20 bars it ordered for two jobs. Receiving notes the shortage on the packing slip and puts it in the purchasing tray. Purchasing finds out three days later, when the second job’s saw date arrives and the material is not there.

If receipts are entered against PO lines when they arrive, the short receipt appears at once on the PO and on both jobs. The scheduler can move the second job and purchasing can chase the supplier the same morning. The information existed the moment the truck was unloaded; it was simply on paper.

An illustration of common patterns in small manufacturers. It describes no real company, customer or result.

BUY, CONFIGURE, CONNECT OR BUILD

Match the fix to your situation.

Inventory and purchasing decisions
Your situationThe sensible move
Inventory lives in QuickBooks items and spreadsheets, and most buying is per jobConfigure purchasing in your ERP so POs tie to jobs. ECI lists automatic PO generation and low-stock alerts in JobBOSS².
You make repeat products to stock and sell online or through distributorsBuy an inventory or MRP product built for that. Katana lists multi-level BOMs and integrations with Shopify, Amazon, WooCommerce, QuickBooks Online and Xero. MRPeasy lists lot, batch and serial tracking, barcodes and one-click purchase orders.
POs are fine, but confirmations, ship dates and certs arrive by emailConnect the supplier emails and certs to the PO, rather than building a purchasing system.
A large customer requires EDI or its portal for ordersSee EDI and portals
Your material rules are unusual and no setting expresses themBuild a small calculation that feeds suggested quantities into the ERP’s purchasing, not a parallel inventory.

THE HONEST PART

When you don’t need custom work.

  • You buy nearly everything to the job. Tie POs to jobs in the ERP and skip formal MRP.
  • Inventory counts are wrong because receipts and issues are not recorded. Fix the habit with barcode scans before blaming the software.
  • Your ERP already has purchasing that nobody configured. Set item types, lead times and reorder points first.

QUESTIONS

Inventory questions, answered plainly.

Short answers. Your own systems and customers decide the details.

Should we count material bought for a specific job as inventory?

Track it against the job, not as general stock. Leftover material worth reusing becomes stock once the job closes, recorded by length or area.

Are barcodes worth it in a small shop?

Usually, for receiving and for issuing material to jobs. A scan is faster than writing and far easier to read later. Start at the receiving dock.

MRP or ERP, which do we need?

MRP is the material-planning part. Many ERPs include it. A shop that mainly sells stocked products may need only MRP plus accounting; a shop running quoted jobs usually needs the job costing an ERP adds.

THE BUSINESS SYSTEMS REVIEW

Bring one late job.
Leave knowing where the material went missing.

In a free 30-minute review we trace one job’s material from PO to saw and show where the information stopped moving.

Book a free 30-minute reviewBook a review

What you leave with

  • Which seam to fix first, and why.
  • What the systems you already pay for can do once configured.
  • Whether anything is worth building. “Nothing” is an acceptable answer.

Free, 30 minutes, no commitment. Bring a redacted example, not drawings, customer records or controlled data.

SOURCES

Vendor descriptions quote or summarize each vendor’s own public page, accessed November 2026. They are examples, not rankings or recommendations. Asterion is not a partner or reseller of any vendor named here. Check current features and editions with the vendor.

LET’S LOOK AT THE REAL WORK

What is your team
working around?

Bring the messy process, something new you want built, or the question of where AI fits. We will work through whether there is a sensible way to improve it.

Book a free 30-minute reviewBook a review

Free, 30 minutes, no commitment.
Start with the problem, not the technology.